Practice 3 for PMP Exam: 25 questions, explained answers, and a review routine.
These questions are for study practice only and are not official exam questions.
Question 1
1
During a retrospective, team members identify recurring interruptions from unplanned requests. What response best supports team ownership?
Question 2
2
A project adds qualified resources to shorten a critical activity and estimates the added cost. What schedule-compression approach is being considered?
Question 3
3
A team is deciding whether to build a feature based on an untested assumption about customer demand. Which next step best reduces waste?
Question 4
4
A portfolio can fund only one of two projects. Project A supports a high-priority strategic outcome; Project B is interesting but has weak strategic relevance. What information is most useful for the decision?
Question 5
5
A project manager receives conflicting status updates from a supplier and the internal team. What is the best next action?
Question 6
6
A project is ending and operational staff will maintain the product. Which closure activity is essential to a usable handover?
Question 7
7
A stakeholder wants a forecast for completing a large backlog. The team has variable historical throughput. Which forecast communicates uncertainty more honestly?
Question 8
8
An organization wants to pilot a service before expanding it nationally. What is a strong purpose for a limited pilot?
Question 9
9
A project has a new team drawn from several departments. What activity is most useful early in the collaboration?
Question 10
10
A required component has already arrived damaged and cannot be used. What is the most appropriate classification of the current problem?
Question 11
11
A product owner wants to add an urgent item during a cycle. The current goal could be affected. What is the best response?
Question 12
12
For a classroom calculation, net benefit equals total benefit minus cost, and return on cost equals net benefit divided by cost. A project costs $50,000 and yields $65,000 in total benefits. What is return on cost?
Question 13
13
A stakeholder needs a monthly decision summary, while engineers need daily technical details. What communication approach best fits these needs?
Question 14
14
A requirements table links each requirement to its source, deliverable, and verification activity. What is the main benefit?
Question 15
15
A retrospective identifies three possible improvements. The team has capacity to test only one next cycle. What is a practical response?
Question 16
16
A business case relies on demand from a market segment that has recently shrunk. What should the project manager do?
Question 17
17
An experienced team is meeting its goals and making sound technical decisions. Which leadership approach is most appropriate?
Question 18
18
A team must choose between two suppliers. Agreed criteria include quality, delivery reliability, support, and price. What approach supports a defensible selection?
Question 19
19
The team is unsure whether users understand a proposed navigation design. What is a useful low-cost experiment?
Question 20
20
A team wants to use an AI-generated summary in an executive decision. Some source records contain unresolved contradictions. What is the most responsible next step?
Question 21
21
A specialist who alone understands a critical component will soon leave the project. What should the manager prioritize?
Question 22
22
A potential supplier delay has not occurred, but it could affect a required component next month. Where should the uncertain event first be tracked with an owner and response?
Question 23
23
Two teams must integrate their work frequently, but each uses a different interpretation of a shared interface. What should they establish?
Question 24
24
In a simplified investment exercise, a project costs $40,000 now and produces net cash benefits of $10,000 at the end of each year. Ignoring discounting, when is the initial cost recovered?
Question 25
25
A stakeholder asks for a technical explanation but repeatedly misinterprets specialist terminology. What is the best communication adjustment?
Enable JavaScript for the interactive step-by-step quiz with instant scoring and explanations.