Contractor License Practice Exam 20

Master contractor license practice exam 20, the hardest, on active-interference delay, CPM windows analysis, total-cost claims, and progressive-collapse design.

Free preview

These questions are for study practice only and are not official exam questions.

Question 1

1

A complex claim: owner-caused suspension of 45 days, during which the contractor demobilized; the contract has a no-damages-for-delay clause with an exception for owner 'active interference.' The contractor's best path to recover delay costs is to:

Question 2

2

A contractor and owner each retain delay experts who produce conflicting CPM analyses. The most persuasive schedule-delay method to a court or arbitrator is generally a:

Question 3

3

A GMP design-build job: GMP $20,000,000, allowance items total $2,400,000, contingency $800,000, fee 4.5% of cost. Actual cost (incl. allowances) is $18,200,000 with $300,000 contingency unspent. The owner's savings (70% of underrun) is: