Contractor License Practice Exam 19

Master contractor license practice exam 19 on concurrent delay, claims-made coverage, earned value, continuous beams, ASCE 7 wind, and IBC occupancy code.

Free preview

These questions are for study practice only and are not official exam questions.

Question 1

1

A contractor faces concurrent delays: a 20-day owner design delay running parallel with a 20-day contractor procurement delay over the same period. Under the dominant U.S. rule on true concurrent delay, the contractor is generally entitled to:

Question 2

2

An owner sues a contractor and its design-build engineer; the engineer's professional liability (E&O) policy is claims-made. A claim first made after the policy lapsed, with no tail coverage, is:

Question 3

3

A design-build team must hit a $12,000,000 GMP. Detailed estimate is $11,300,000 direct + indirect; the team carries a 4% design contingency and 5% fee on the subtotal. Does the estimate fit under the GMP?