Master contractor license practice exam 18 on surety completion loss, comparative fault, GMP savings, transfer girders, P-M columns, and IBC high-rise code.

Free preview

These questions are for study practice only and are not official exam questions.

Question 1

1

A prime defaults; the surety completes the work and incurs $1,200,000 over the remaining contract balance of $900,000. The surety's net loss it will seek from the indemnitors is:

Question 2

2

A multi-party claim allocates fault: owner 30% (defective design, Spearin), contractor 50% (workmanship), subcontractor 20%. On $1,000,000 of damages in a comparative-fault state, the contractor's direct share is:

Question 3

3

A design-build GMP is $8,000,000 with a 60/40 owner/contractor savings split and a $200,000 contingency that is shared if unspent. Actual cost is $7,500,000 and $150,000 of contingency was unused. The contractor's total savings share is computed on: