Question 1

1

A multi-tier dispute: the owner withholds $180,000 from the GC for alleged defects; the GC, under a pay-if-paid clause, withholds from the drywall sub whose work is not at issue. In a state that bars pay-if-paid as against public policy, the GC most likely:

Question 2

2

An EMR of 0.85 versus 1.20 on a $400,000 manual workers' comp premium base produces an annual premium difference of:

Question 3

3

A self-performed earthwork job moves 18,000 BCY (bank). The soil has a 25% swell. How many LCY (loose) must be hauled?