Advanced contractor license practice exam 14 on termination for convenience, CGL exclusions, productivity loss, WIP accounting, and IBC fire and egress code.

Free preview

These questions are for study practice only and are not official exam questions.

Question 1

1

A GC terminates a subcontractor 'for convenience.' Under a typical termination-for-convenience clause, the sub is generally entitled to:

Question 2

2

A contractor's CGL policy contains a 'your work' exclusion. This exclusion typically bars coverage for:

Question 3

3

A project's labor is $300,000, materials $450,000, equipment $80,000, subs $200,000. The contractor adds 8% overhead on all direct cost and 6% profit on the resulting subtotal. What is the bid?