Practice test

Contractor License Practice Exam 13

Advanced contractor license practice exam 13 on statutes of repose, indemnity, equipment cost, percentage-of-completion, and IBC occupancy and fire-wall rules.

Free preview

These questions are for study practice only and are not official exam questions.

Question 1

1

A GC receives a defective-work claim 4 years after substantial completion in a state with a 10-year statute of repose and a 2-year discovery statute of limitations. The defect was discovered 3 months ago. The claim is most likely:

Question 2

2

An indemnification clause requires the sub to indemnify the GC for losses 'caused in whole or in part by the sub, regardless of whether caused in part by the GC.' In many states, indemnifying another party for that party's own negligence is:

Question 3

3

A contractor bids 320 LF of footing requiring 0.5 CY of concrete per LF, ordered with 7% waste, at $165 delivered per CY. What is the concrete material cost?

Enable JavaScript for the interactive step-by-step quiz with instant scoring and explanations.