Question 1
Question 2
A multi-party claim allocates fault: owner 30% (defective design, Spearin), contractor 50% (workmanship), subcontractor 20%. On $1,000,000 of damages in a comparative-fault state, the contractor's direct share is:
Question 3
A design-build GMP is $8,000,000 with a 60/40 owner/contractor savings split and a $200,000 contingency that is shared if unspent. Actual cost is $7,500,000 and $150,000 of contingency was unused. The contractor's total savings share is computed on: