Question 1

1

A GC terminates a subcontractor 'for convenience.' Under a typical termination-for-convenience clause, the sub is generally entitled to:

Question 2

2

A contractor's CGL policy contains a 'your work' exclusion. This exclusion typically bars coverage for:

Question 3

3

A project's labor is $300,000, materials $450,000, equipment $80,000, subs $200,000. The contractor adds 8% overhead on all direct cost and 6% profit on the resulting subtotal. What is the bid?